01 / SOLAR PLANNING
How much solar can fit?
Count full modules on a rectangular roof, with explicit setbacks and row gaps. Add identical roofs to scale the estimate.
Calculation method & assumptions
Full rows only: modules per row × rows × module Wp / 1,000. The row depth is the module slope length × cos(tilt); gaps occupy horizontal space. Setbacks apply to all four edges. No inter-module gaps, obstacles, roof slope, aisle rules, structural limits or automatic shading allowances are included. Use row spacing below to choose a gap; actual layout may fit fewer modules.
02 / SOLAR PLANNING
Turn capacity into energy.
Use your first-year specific yield to explore annual generation and lifetime degradation. For a location-based estimate, start with our NASA POWER irradiation tool.
Calculation method & assumptions
Year 1 energy = DC capacity × first-year specific yield. Year n = year 1 × (1 − annual degradation)^(n − 1). The input yield already includes year-one system losses. This is a fixed-yield projection; it does not model hourly weather, tracking, clipping or annual variability. The irradiation calculator supplies monthly climate-based estimates and CSV export.
03 / SOLAR PLANNING
Build your project budget.
Enter current quotations in the selected project currency. Nothing here is an automatic market price.
Calculation method & assumptions
Each unit-price item = project kWp × 1,000 × quoted price per Wp. Subtotal = line items + other fixed costs; contingency applies to that subtotal. Tax is included only if included in your quotations. Annual roof rent and operating costs belong in the returns tool. A budget is not a supplier quotation.
04 / SOLAR PLANNING
Explore the project cash flow.
Compare project and financed-equity cash flows using your tariffs, costs, degradation and loan terms. Expand the annual table to see what drives the result.
Calculation method & assumptions
Annual value = generation × [self-use share × avoided import tariff + exported share × export tariff]. Tariffs and operating costs escalate independently; energy degrades after year 1. Project cash flow deducts operating and replacement costs. Equity cash flow additionally deducts annual end-of-year level-payment debt service; year 0 is the equity contribution. NPV discounts each end-of-year cash flow; IRR is shown only for a conventional investment with a unique root. Payback interpolates the cumulative recovery that remains nonnegative through the modeled horizon, including later replacement expenses. No taxes, subsidies, depreciation, salvage value, transaction fees, time-of-use matching or fixed bill charges. Self-use is an input, not an hourly simulation. NREL SAM financial models cover more detailed project structures.
05 / SOLAR PLANNING
Bring the plan to your project team.
Use LuminVolt’s existing product and engineering resources, and prepare the information needed for a project-specific proposal.
Solar mounting systems
Explore roof and ground structures for your mounting configuration.
Single-axis solar trackers
Review the tracker product information before discussing the site configuration.
Structural load calculator
Continue to the existing structural calculator for its stated loading assumptions.
Wind & snow load calculator
Review site wind and snow inputs in the existing load tool.
Climate & irradiation data
Use NASA POWER monthly climate data in the companion solar resource calculator.
Before you request a proposal
- Site location, roof or ground survey, usable dimensions and obstruction photos.
- Module and inverter datasheets, array configuration and proposed cable routes.
- Local wind, snow, structural and electrical requirements.
- Electricity bill, export contract and current equipment quotations.
This section links to LuminVolt resources. It is not a third-party installer directory or an endorsement of an external contractor. No project information is sent automatically.
06 / SOLAR PLANNING
Leave room for the winter sun.
Estimate a clear row gap and front-to-front pitch on level ground over a chosen solar-time window. Bearings are clockwise from true north.
Calculation method & assumptions
On level ground, projection = row slope length × cos(tilt), height difference = row slope length × sin(tilt). Gap = the largest shadow component normal to the rows while the sun is in front of the array, sampled every 5 minutes over your solar-time window. Pitch = projection + gap. Only the selected date and time window are checked; below-horizon times are flagged. No terrain slope, finite-row edge effects, diffuse shading or energy-loss model. Solar position uses a simplified declination model, not a surveying ephemeris. NOAA solar geometry reference.
07 / SOLAR PLANNING
Trace an obstacle’s shadow.
Explore the flat-ground shadow from a vertical object. East and north coordinates show where the tip falls relative to the object.
Calculation method & assumptions
Shadow tip east = −height × sun east / sun up; north = −height × sun north / sun up. Coordinates are relative to the obstacle’s base; shadow direction is opposite the sun. The diagram and 30-minute table describe a vertical point object on horizontal ground. Width, terrain, panel-plane intersections, vegetation, obstructions and resulting energy loss are not modeled. Times are local apparent solar time, not civil clock time.
08 / SOLAR PLANNING
Check cable voltage drop.
Compare conductor sections for a known circuit. Keep voltage-drop screening separate from the cable’s installation-specific current rating.
Calculation method & assumptions
Resistance uses conductor resistivity at 20°C corrected to the entered conductor temperature. DC/single-phase loop length is twice the one-way route; three-phase drop uses √3 × one-way resistance × current × power factor. AC reactance is set to zero. Loss is I²R for each loaded conductor. Candidate sections meet only the entered voltage-drop limit. A supplied derated ampacity is compared to operating current separately; no automatic ampacity table, protective-device coordination, fault withstand, harmonics or local-code verification is provided. Schneider Electric voltage-drop equations.
09 / SOLAR PLANNING
The details that make a difference.
A compact collection of PV electrical checks, geometry conversions and project comparisons. All factors and assumptions stay visible.
PV string voltage range
Enter module voltage coefficients from the actual datasheet. Coefficients are percent per °C, not fractions.
V(T) = V(25°C) × [1 + coefficient / 100 × (T − 25)]. Both temperature endpoints constrain the range. The result checks operating MPPT and absolute DC voltage only; inverter start voltage, current, optimizers and cold-weather design margins still need separate checks. Example voltages are not a named product specification.
Solar time ↔ clock time
Enter the UTC offset actually in effect, including daylight saving if applicable.
NOAA equation-of-time approximation: solar minutes = clock minutes + 4 × longitude − 60 × UTC offset + equation of time. Both conversion directions use the same entered time. Results wrap over midnight with a day-offset label. NOAA equations.
Slope ↔ tilt angle
Convert a percentage grade to an angle, and an angle to grade.
Grade (%) = 100 × tan(angle). The two input values are converted independently.
Tilt components ↔ full tilt
Azimuth is the surface facing direction measured clockwise from north.
North component = atan[tan(tilt) × cos(azimuth)]; east = atan[tan(tilt) × sin(azimuth)]. The second pair is independently inverted to tilt and azimuth. Signs refer to the facing-vector components.
Avoided emissions estimate
Use an emission factor appropriate to your grid, period and accounting method.
Avoided emissions = displaced kWh × entered kg CO₂e/kWh. This excludes lifecycle emissions and does not establish additionality or a certified carbon credit. No default grid factor is assumed.
Compare two investment options
Enter the incremental cost and first-year benefit of option B versus option A.
Incremental cash flow = benefit × (1 − degradation)^(year − 1) − additional operating cost, with the extra investment at year 0. The same project currency is used for both alternatives; no financing, taxes, escalation or residual value.
Bifacial irradiation contribution
Enter modeled front and rear irradiation and the module bifaciality from its datasheet.
Irradiance contribution gain = rear / front × bifaciality. This screening ratio excludes spectral, mismatch, thermal and electrical losses. It does not infer rear irradiation from albedo, clearance or row pitch; use a rear-irradiance model for those geometry effects.